Date: 23/11/2006 |
|
| Click on the image for a bigger view. |
|
|

Overall
|
|

Plot 1 - 14 1st floor beam in progress. Formwork erected.
|
|
|
|

Plot 17 - 20 Superstructur completed. Brick-up completed up to 90%.
|
|

Plot 21 - 25 Metal Roof Trusses in progress.
|
|
|
|

Plot 26 - 21 Superstructure completed. Brickworks in progress.
|
|

Plot 31 - 37 Superstructure completed. Brickwork to be started.
|
|
|
|

Plot 38 - 43 Superstructure completed. Brickwork to be started.
|
|

Plot 44 - 50 Roof beam in progress.
|
|
|
|

Plot 51 - 54 2nd floor slab in progress.
|
|

Staircase landing & riser in progress.
|
|