Date: 23/01/2007 |
|
| Click on the image for a bigger view. |
|
|

Bird Eye View of Ferringhi Park
|
|

Plot 1 - 6 Superstructure Completed. Bricks Works in Progress
|
|
|
|

Plot 17 - 20 Under Coat Completed. External Painting Partially Completed at Plot 17 & 18
|
|

Plot 26 - 31 Roofing Works Completed. Internal & External Plastering Completed. Under Coat Completed
|
|
|
|

Plot 32-37 Roofing Works in Progress. Internal & External Plastering Completed. Approximately 80% of Under Coat Completed.
|
|

Plot 51 - 54 Brick Works Completed. Roof Tiles in Progress up to 70% Completion.
|
|
|
|

Plot 51 - 54 Brick Works Completed. Roof Tiles Laying in progress
|
|

Roofing Works Completed. Internal & External Plastering Completed. Under Coat Completed.
|
|