Date: 16/05/2007 |
|
| Click on the image for a bigger view. |
|
|

Ferringhi Park signage of open space in progress.
|
|

Plot 19 - 20 Gate post & ext. fencing in progress
|
|
|
|

Plot 19 - Timber staircase on 1st floor in progress
|
|

Plot 21, 50 & 57 - Roofing works 80% completed. Ext. plastering in progress for 3 bungalows
|
|
|
|

Plot 22 - 25 Gate post, ext. fencing & drainage in progress
|
|

Plot 32 - 37 Building finishes in progress. Ext. U drain & fencing in progress
|
|
|
|

Plot 43 - Ext.fence & U drain in progress
|
|

Phase 2 Show House Type A - Internal plastering in progress
|
|
|
|

Phase 2 Show House Type B - Roof tiles in progress, plastering in progress
|
|