Date: 14/03/2007 |
|
| Click on the image for a bigger view. |
|
|

Bungalow Plot 21. Substructure Completed (Foundation & Ground Beam). Superstructure in Progress up to 1st Floor Column.
|
|

Bungalow Plot 50. Substructure Completed (Foundation & Ground Beam). Superstructure in Progress up to 2nd Floor Beam with Formwork
|
|
|
|

Bungalow Plot 57. Substructure Completed (Foundation & Ground Beam). Superstructure in Progress up to 2nd Floor Beam with Formwork
|
|

Phase 1 Open Park. Setting out completed. Site Clearance Completed. Hardscape in progress.
|
|
|
|

Plot 1 - 16 Internal & External Plastering Completed. Base Coat of Painting in Progress. Roofing Work in Progress
|
|

Plot 17 - 20 Internal & External Plastering Completed. Final Coat of Painting in Progress. Roofing Work Completed. Door & Window Frame Completed.
|
|
|
|

Plot 22-25 Internal & External Plastering Completed. Final Coat of Painting in Progress. Roofing Work Completed. Door & Window Frame Completed
|
|

Plot 26-31Internal & External Plastering Completed. Final Coating in Progress. Roofing Work & Painting in Progress. Door & Window Frame Completed.
|
|
|
|

Plot 32-37 Internal & External Plastering Completed. Final Coat of Painting in Progress. Roofing Work Completed. Door & Window Frame Completed.Roofing Work in Progress
|
|

Plot 38-43 Internal & External Plastering Completed. Final Coat of Painting in Progress. Roofing Work Completed. Door & Window Frame Completed.Frame Completed.
|
|
|
|

Plot 44-49 Internal & External Plastering Completed. Base & Final Coat of Painting in Progress. Roofing Work in Progress. Door & Window Frame in Progress.
|
|

Plot 51- 54 Internal & External Plastering Completed. Base & Final Coat of Painting in Progress. Roofing Work in Progress. Door & Window Frame in Progress.
|
|