Date: 09/04/2007 |
|
| Click on the image for a bigger view. |
|
|

Phase 2 Show House - Type A, roof beam in progress.
|
|

Phase 2 Show House - Type B, 2nd floor beam & slab in progress
|
|
|
|

Plot 1-16. Aluminium sliding door and window in progress. Internal sanitary work completed but manhole in progress. Wall tile completed.
|
|

Plot 17-20. Aluminium sliding door and window completed. Internal sanitary and manhole completed. Car porch concrete imprint in progress. Wall tile completed. Glazing work completed.
|
|
|
|

Plot 21 Bungalow. Foundation work completed. Superstructure work completed. Internal sanitary and plumbing in progress.
|
|

Plot 22-25. Aluminium sliding door and window completed. Internal sanitary and manhole completed. Car porch concrete imprint in progress. Wall tile completed. Glazing work completed.
|
|
|
|

Plot 26-31. Aluminium sliding door and window completed. Internal sanitary and manhole completed. Car porch concrete imprint in progress. Wall tile completed. Glazing work completed.
|
|

Plot 32-37. Aluminium sliding door and window completed. Internal sanitary and manhole completed. Car porch concrete imprint in progress. Wall tile completed. Glazing work completed.
|
|
|
|

Plot 38-43. Aluminium sliding door completed. Internal sanitary completed but manhole in progress. Wall tile completed. Glazing work in progress.
|
|

Plot 44-49. Aluminium sliding door completed. Internal sanitary completed but manhole in progress. Wall tile completed. Glazing work in progress.
|
|
|
|

Plot 50 Bungalow. Foundation work completed. Superstructure work completed. Internal sanitary and plumbing in progress.
|
|

Plot 51-54. Aluminium sliding door completed. Internal sanitary completed but manhole in progress. Wall tile completed. Glazing work in progress.
|
|
|
|

Plot 57 Bungalow. Foundation work completed. Superstructure work completed. Internal sanitary and plumbing in progress.
|
|